Major Capital Projects Dashboard

Major Capital Projects Dashboard

Progress Report to reflect project statuses for the 4th quarter of 2021.

This dashboard displays statuses of all major projects to include new/replacement schools, systemic replacements and interior renovations with a budget in excess of $10M.

 Orange symbol indicates a project may have budget or schedule concerns--there are issues that bear monitoring.

 Red symbol indicates a project has significant budget and/or schedule concerns--there are issues to be addressed.

 Green symbol indicates the project is on schedule and on budget--there are no pending issues of concern.


How To Navigate the Capital Projects Dashboard

Project/School/Facility Status Budget Planning/Design Start Construction Start Phase & Percentage General Overview Status Project Team Notes Project ID Photos
Andrew Jackson Academy HVAC $17,641,000 2016 September 2020 Construction Phase 40% Systemic Renovation: Replace 1971 HVAC equipment including one (1) chiller, 14 air handling units, heating and cooling piping, and the controls system, replace one (1) 1996 cooling tower, and replace two (2) 2000 steam boilers with hot water boilers. Continue schedule construction activities. Architect: Kibart; Construction Manager: Keller Construction Management; PGCPS Project Manager: Henry Lewis PSC 16.197.18 SR Priority 29
Bowie-Belair High Annex $25,865,000 2014 December 2019 Construction Phase 32% Limited renovation and improvements to the existing special education program. Includes (5) major systemic projects in addition to educational program enhancements. All Phase 1 areas are occupied. Continue construction activities scheduled for Phase 2a-2b. Architect: DLR Group; Contractor: Hess Construction; PGCPS Project Manager: Hiwot Haileselassie PSC 16.041.19 C, Priority # 3
Central HS HVAC $20,218,000 2016 March 2020 Construction Phase 78% Systemic Renovation: Replace the entire 1982 heating and ventilating system with a complete heating, ventilating and air conditioning system, including boilers, chiller, rooftop units, air handling units, terminal units, piping, and controls. Principal and Students/Community Governing Body working on Re-Branding themes, 3 meetings were organized, follow-up in progress. Principal provided the electronic file and was forwarded to Architect for review and comment. Testing in planned on PVI Water Heater Factory Startup. Re-Branding work in progress. Community Presentation conducted, May 4th. Relocation from Forestville started June 15th, coordination continues. Architect: Gipe Associates, Inc.; Construction Manager: Oak Contracting LLC; PGCPS Project Manager: Anoop Gupta PSC 16.010.18 SR, Priority #28
Cherokee Lane ES $34,000,000 2019 April 2020 Construction Phase 28% Replacement of a new school with 95,000 sf on a new site, for 846 SRC. Phase 1 off-site construction, 75% complete; expected on-site delivery Summer 2021. Phase 2 site work 7% complete. Architect: Gilbert Architect, Inc.; Construction Manager: Whiting & Turner Contracting; PGCPS Project Manager: Joseph Howell PSC 16.267.20 C, Priority #11 Photos
Cool Spring Annex-Judy Hoyer Ctr. $ 2019 January 2020 Planning Phase 50% Renovation, addition and conversion of a 58,000 SF annex building with existing office spaces into additional 560 student elementary school space. Development of the Request for Proposal to solicit Architectural/Engineering services. PGCPS Contact: Ronald Kauffman, Planner II
New Glenridge Area MS $80,000,000 2017 April 2020 Construction Phase 0% Construction of a new 160,900 sf and 1,180 SRC middle school in the Glenridge area. Selection and award of construction contractor. Submit construction contract to Interagency Commission for approval. Architect will prepare site plan to address Park and Planning amenities design for community purposes and use. Architect: Grimm and Parker; Construction Manager: MCN Build; PGCPS Project Manager: Hiwot Haileselassie PSC 16.265.20 C, Priority #4 Photos
High Point HS $189,000,000 2018 January 2020 Planning Phase 95% Modernization/additions to the existing 2081 seat (SRC) high school to create a 2500 seat high school on the same site. Review responses to the Architectural/Engineering RFP. Architect: TBD; Contractor or Construction Manager: TBD; PGCPS Planner: Joseph Wolf
International HS @ Langley Park $34,000,000 2016 September 2020 Design Phase 35% New school 58,000 sf, including cooperative use space, for 400 SRC. Design Development forwarded to MSDE for review and approval February 2021. Architect: DLR Group; Contractor or Construction Manager: TBD; PGCPS Project Manager: Hiwot Haileselassie
New Northern Adelphi Area HS $ 2019 January 2020 Planning Phase 39% Construction of a new 369,806 SF and 2,600 student high school in the Adelphi area. Continue scheduled Project Planning Committee (PPC) meetings. PGCPS Contact: John Wooden
Stephen Decatur MS SEI $10,501,000 2014 September 2020 Construction Phase 40% Special Education Inclusion Renovation: Renovate 11,240 net sq. ft. (17,000 GSF) in the southeast corner of the building for the CRI/Regional Program and an added space for the therapy pool to serve the regional students in the area. Permit for modulars is under review by third-party reviewer. Site work at auxiliary parking log ongoing. Swimming pool addition work activities in progress to include: installed plumbing groundwork, men's locker room, pouring of slab, and installation of electrical work for future construction phases. Summer work: start of construction at kitchen, weight room, and vestibule. Continue scheduled construction activities at addition. Architect: CRA Architects; Contractor: Keller Brothers, Inc.; PGCPS Project Manager: Henry Lewis PSC 16.143.16 C, Priority #2
Suitland HS $227,758,000 2017 January 2022 Design Phase 50% Full Renovation and/or Replacement of the existing 344,875 SF Suitland High School Campus Schematic phase review response completed and sent to Maryland State Department of Education in Spring 2021. Structural remediation work contract awarded. Commence preparation of Construction Management at Risk (CMR) procurement documents. Issue Request for Proposal to solicit CMR services. Feasibility Study: Grimm and Parker; Design Architect: Cox Graae + Spack Architects; Contractor or Construction Manager: TBD; PGCPS Contact: Ronald Kauffman
William Schmidt Outdoor Ed. Center $32,000,000 2016 March 2021 Design Phase 75% Modernization of and upgrades to the Center, to include construction of a second residential village, central dining hall, and environmental learning center as well as modernization of the Village I complex and modernization/adaptive reuse of the Orme Building. Finalize construction management as advisor/agent (CMa) solicitation; advertise for construction services. Submit construction documents to Department of General Services for approval. Evaluate CMA proposals; recommendation of award. Architect: Quinn Evans; Contractor or Construction Manager: TBD; PGCPS Contact: Joseph Wolf PSC 16.199.18 C, Priority #5
William Wirt MS $85,000,000 2017 April 2021 Construction Phase 0% Demolition of the existing 106,318 SF facility built in 1964 with a State Rated Capacity (SRC) of 850 students and replacement with a new 170,900 SF facility with a SRC of 1,200 students at the same site. Construction contract was awarded and approved by the Interagency Commission. Third Party Inspection Services procurement and selection. Architect: Crabtree, Rohrbaugh & Associates; Contractor or Construction Manager: TBD; PGCPS Project Manager: Henry Lewis PSC 16.183.20 C, Priority #2 Photos