Major Capital Projects Dashboard

Major Capital Projects Dashboard

Progress Report to reflect project statuses for the 4th quarter of 2022.

This dashboard displays statuses of all major projects to include new/replacement schools, systemic replacements and interior renovations with a budget in excess of $10M.

 Orange symbol indicates a project may have budget or schedule concerns--there are issues that bear monitoring.

 Red symbol indicates a project has significant budget and/or schedule concerns--there are issues to be addressed.

 Green symbol indicates the project is on schedule and on budget--there are no pending issues of concern.


How To Navigate the Capital Projects Dashboard

Project/School/Facility Status Budget Planning/Design Start Construction Start Phase & Percentage General Overview Status Project Team Notes Project ID Photos
Andrew Jackson Academy HVAC $17,641,000 2016 September 2020 Construction Phase 92% Systemic Renovation: Replace 1971 HVAC equipment including one (1) chiller, 14 air handling units, heating and cooling piping, and the controls system, replace one (1) 1996 cooling tower, and replace two (2) 2000 steam boilers with hot water boilers. Completion of balancing, punchlist, commissioning, final inspections. Architect: Kibart; Construction Manager: Keller Construction Management; PGCPS Project Manager: Henry Lewis PSC 16.197.18 SR Priority 29
Bowie-Belair High Annex $25,865,000 2014 December 2019 Construction Phase 97% Limited renovation and improvements to the existing special education program. Includes (5) major systemic projects in addition to educational program enhancements. All phases for classrooms, offices and admin areas have received temporary occupancy. Architect: DLR Group; Contractor: Hess Construction; PGCPS Project Manager: Hiwot Haileselassie PSC 16.041.19 C, Priority # 3
Central HS HVAC $20,218,000 2016 March 2020 Construction Phase 97% Systemic Renovation: Replace the entire 1982 heating and ventilating system with a complete heating, ventilating and air conditioning system, including boilers, chiller, rooftop units, air handling units, terminal units, piping, and controls. Final close out items in progress: final inspections and training. Architect: Gipe Associates, Inc.; Construction Manager: Oak Contracting LLC; PGCPS Project Manager: Anoop Gupta PSC 16.010.18 SR, Priority #28
Charles Herbert Flowers HS HVAC Renovation $11,168,241 2019 June 2022 Design Phase 0% Replace the 1999 HVAC System Architect/Engineer meeting scheduled for June and July. Development of design procurement solicitation documents for release. 16.174.21 SR, PRI# 10
Cherokee Lane ES $34,000,000 2019 April 2020 Construction Phase 90% Replacement of a new school with 95,000 sf on a new site, for 846 SRC. Phase - 1 - Modular Bldg. - 91% Complete. Remaining Items: - Punch List Completion. - Official receipt of U&O from DPIE. DPIE has provided unofficial approval. -Equipment start - up and training for PGCPS personnel - Commissioning kick-off meeting 6/14 - Receipt of FF & E - Deliveries start 6/29 & 6/30. (desks & Tables) Chairs start arriving July 14th. Cafeteria Tables - mid August. Will use exiting tables from St. Marks in the meantime -Interior Graphics to commence by end of June Phase -2 - Sitework approximately 81 % . Paving 100% - Completed Playground Equipment - 100% Completed Storm water management sys - 100% completed Remaining Item(s): Completion of the playing fields Architect: Gilbert Architect, Inc.; Construction Manager: Whiting & Turner Contracting; PGCPS Project Manager: Joseph Howell PSC 16.267.20 C, Priority #11 Photos
Cool Spring Annex-Judy Hoyer Ctr. $ 2019 January 2020 Planning Phase 50% Renovation, addition and conversion of a 58,000 SF annex building with existing office spaces into additional 560 student elementary school space. Development of the Request for Proposal to solicit Architectural/Engineering services. PGCPS Contact: Ronald Kauffman, Planner II
Dwight Eisenhower Middle School HVAC Renovation $12,063,600 2022 July 2022 Design Phase 49% HVAC & Building Envelope / Replace the 1969-1974 central controls system, HVAC piping, all ten (10) AHUs, 45 finned tube radiators, four (4) self-contained unit ventilators, 17 floor mounted fan coil units, two (2) ceiling mounted AHUs, chiller Windows and Doors component of the project is complete. HVAC Design continues. Evaluations complete. Architect/Engineer: Global Engineering SolutionContractor: The Matthews Group (TMG)PGCPS Project Manager: Anoop Gupta 16.008.19 SR, PRI# 12
New Glenridge Area MS $80,000,000 2017 December 2021 Construction Phase 0% Construction of a new 160,900 sf and 1,180 SRC middle school in the Glenridge area. Document for Final Land swap is circulating in PGCPS and Park and Planning. - Site Permit has been attained. - Silt Fence has been inspected on 04/28/22. Inspector has noted a violation and Contractor has paid $1,000 fine. - Geothermal well location approval permit has been attained. Architect: Grimm and Parker; Construction Manager: MCN Build; PGCPS Project Manager: Hiwot Haileselassie PSC 16.265.20 C, Priority #4 Photos
High Point HS $189,000,000 2018 January 2020 Planning Phase 95% Modernization/additions to the existing 2081 seat (SRC) high school to create a 2500 seat high school on the same site. Review responses to the Architectural/Engineering RFP. Architect: TBD; Contractor or Construction Manager: TBD; PGCPS Planner: Joseph Wolf
International HS @ Langley Park $34,000,000 2016 September 2020 Design Phase 35% New school 58,000 sf, including cooperative use space, for 400 SRC. Design Development forwarded to MSDE for review and approval February 2021. Architect: DLR Group; Contractor or Construction Manager: TBD; PGCPS Project Manager: Hiwot Haileselassie
James Madison Middle School HVAC Replacement $10,421,000 2020 June 2022 Construction Phase 0% Replacement of HVAC piping system, chiller, cooling tower, four (4) air handling units, 96 mixing boxes, twenty (20) finned tube radiators, fifteen (15) convectors, and controls. In construction; On schedule; Vendor Protec Construction is working on site, Construction Sign is installed; Miss Utility work is complete; Sprinkler rough-in is progress; New Water WSSC pipeline mobilization in progress; coordination with the Principal and Building Supervisor in progress. Contractor: Protec Construction Inc.; PGCPS Project Manager: Anoop Gupta 16.114.20 SR, PRI# 12
New Northern Adelphi Area HS $ 2020 July 2022 Planning Phase 75% Construction of a new 369,806 SF and 2,600 student high school in the Adelphi area. Current Status: Continue scheduled Project Planning Committee (PPC) meetings. Upcoming Activities: Completion of Schematic Design (SD) phase. Architect/Engineer: Gilbert Architects, Inc.; Contractor: TBD; PGCPS Contact: Joseph Howell
Robert Goddard Montessori HVAC Renovation $16,047,000 2016 June 2020 Construction Phase 95% Systemic Renovation: Replace / upgrade the 1964 106,701 SF school building and 1966 26,930 SF addition mechanical system, composed of two gas fired steam boilers and one chiller. Projected completion anticipated for Spring 2022. Architect: Gannett Fleming, Inc.; Contractor: Fresh Air Concepts, LLC; PGCPS Contact: Sean Nickols, Project Manager II 16.181.18 SR, PRI# 46
Stephen Decatur MS SEI $10,501,000 2014 September 2020 Construction Phase 75% Special Education Inclusion Renovation: Renovate 11,240 net sq. ft. (17,000 GSF) in the southeast corner of the building for the CRI/Regional Program and an added space for the therapy pool to serve the regional students in the area. The completion date for the entire project is December 2022. Pool completion scheduled for July. Architect: CRA Architects; Contractor: Keller Brothers, Inc.; PGCPS Project Manager: Henry Lewis PSC 16.143.16 C, Priority #2
Suitland HS $227,758,000 2017 January 2022 Design Phase 95% Full Renovation and/or Replacement of the existing 344,875 SF Suitland High School Campus Schematic phase review response completed and sent to Maryland State Department of Education in Spring 2021. Structural remediation work contract awarded. Commence preparation of Construction Management at Risk (CMR) procurement documents. Issue Request for Proposal to solicit CMR services. Feasibility Study: Grimm and Parker; Design Architect: Cox Graae + Spack Architects; Contractor or Construction Manager: TBD; PGCPS Contact: Sean Nickols
William Schmidt Outdoor Ed. Center $32,000,000 2016 March 2021 Design Phase 100% Modernization of and upgrades to the Center, to include construction of a second residential village, central dining hall, and environmental learning center as well as modernization of the Village I complex and modernization/adaptive reuse of the Orme Building. Finalize construction management as advisor/agent (CMa) solicitation; advertise for construction services. Submit construction documents to Department of General Services for approval. Evaluate CMA proposals; recommendation of award. Architect: Quinn Evans; Contractor or Construction Manager: TBD; PGCPS Contact: Joseph Wolf PSC 16.199.18 C, Priority #5
William Wirt MS $85,000,000 2017 April 2021 Construction Phase 8% Demolition of the existing 106,318 SF facility built in 1964 with a State Rated Capacity (SRC) of 850 students and replacement with a new 170,900 SF facility with a SRC of 1,200 students at the same site. Current Status: Areas A&B foundations completed; Foundations for Area C nearing completion; Slab on grade installed at gym. CMU walls being constructed at Area A; Underground plumbing and electrical installation. Upcoming Actions: CMU walls, slab on grade, underground plumbing and underground electrical. Architect: Crabtree, Rohrbaugh & Associates; Contractor or Construction Manager: TBD; PGCPS Project Manager: Henry Lewis PSC 16.183.20 C, Priority #2 Photos