School Information
- Principal: Cecil Miller, Ed.S
- Address: 8200 Pinewood Drive, Clinton, MD
20735
- Neighborhood: Clinton
- County Council District: District 8 (Edward
Burroughs, III)
- State Legislative District: District 27 A
(Senator Michael Jackson, Delegate Elizabeth Proctor)
- School Board Member: District 9 (Sonya
Williams)
Scope of Work
Special Education Inclusion Renovation: Construction of a new
therapy pool addition, and renovation of the existing building in several
phases over approximately three years.
Project Details
- Budget: $15,105,800
- Planning/Design Start: 2014
- Construction Start: September 2020
- Phase & Percentage Complete: Construction; 95%
- Progress
to Date: Phases 1,4, 5, 5A and 6 have been completed and turned over to the school.
- Current
Status:
- Phase 1: Pool - Substantial completion. Health inspection remains.
- Phase 4: Classrooms: Substantial completion. Turned over to school.
- Phase 5: Substantial completion 8/17/22. Turned over to school.
- Phase 5A: Substantial completion 8/29/22. Turned over to school.
- Phase 6: Substantial completion 8/17/22. Turned over to school.
- Phase 7: Construction continuing. Mechanical ductwork installed. CMU works ongoing. Trenching and concrete backfill for underground plumbing completed. Metal wall studs installed. Turnover to school expected in December 2022.
- Site: Paving completed.
- Upcoming Activities:
- Phase 1 Pool Addition – Punchout and health inspection.
- Phase 5 -Punchout.
- Phase 5A – Punchout.
- Phase 6- Punchout.
- Phase 7 – Ceiling grid and flooring. New electrical transformer switchover.
- Project Team: