William Wirt Middle School

William Wirt MS 190912

Scope of Work

Demolition of the existing 106,318 SF facility built in 1964 with a State Rated Capacity (SRC) of 850 students and replacement with a new 170,900 SF facility with a SRC of 1,200 students at the same site. 

Project Details

  • Budget: $85,000,000 
  • Planning/Design Start: 2017 
  • Construction Start: Spring 2021
  • Phase & Percentage Complete: Pre-construction; 70%
  • Current Status: Completed third party review of permit. Health Department approval received. Site and WSSC reviewing ongoing. 
  • Upcoming Actions: Evaluation of bids received from four (4) pre-qualified contractors. Approval of permit drawing. Solicitation of third party inspection services. 
  • Project Team:
  • PGCPS Contact: Henry LewisProject Manager II

Project Documents


QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 3/5/2021 9:31:36 AM