New Glenridge Area Middle School

GMS Commons View 191007

Scope of Work

Construction of a new 160,900 SF and 1,180 SRC middle school in the Glenridge area to alleviate current overcrowding in neighboring schools & meet the demands of projected enrollment.

Project Details

  • Budget: $80,000,000 
  • Planning/Design Start: 2017 
  • Construction Start: May 2021
  • Phase & Percentage Complete: Contractor Procurement; 75%
  • Current Status: Request for Proposal issued to pre-qualified contractors, February 2021. Permit drawings are approved by third party reviewer and have been submitted to DPIE for review and approval. Architect working to complete site concept plan for replacement of amenities to facilitate the land exchange between PGCPS and M-NCPPC.
  • Upcoming Actions: Selection and award of construction manager. Approval of permit drawings. Meet with M-NCPPC to discuss proposed amenities concept plan.   
  • Project Team:
  • PGCPS Contact: Hiwot Haileselassie, Project Manager II

 


QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 3/5/2021 8:40:26 AM