School Information
- Principal: TBD
- Address: TBD
- Neighborhood: Adelphi
- County Council District: District 2 (Deni
Taveras)
- State Legislative District: District 47
(Senator Malcolm Augustine, Delegate Diana Fennell, Delegate Wanika Fisher, and
Delegate Julian Ivey)
- School Board Member: District 3 (Pamela
Boozer-Strother)
Scope of Work
Construction of a new 369,806 SF and 2,600 student high school in the Adelphi area to alleviate current overcrowding in neighboring schools and meet the demands of projected enrollment.
Project Details
- Design Budget: $7,000,000.00
- Planning/Design Start: 2020
- Construction Start: TBD
- Phase & Percentage Complete: Planning; 80%
- Current Status: Continue scheduled Project Planning Committee (PPC) meetings.
- Upcoming Activities: Completion of Schematic Design (SD) phase.
- Project Team:
- Architect: Gilbert Architects, Inc.
- Construction Manager or Contractor: TBD
- PGCPS Contact: Joseph Howell, Senior Project Manager
Project Documents
- Project Planning Committee (PPC) Meeting Minutes