High Point High School

HPHS Feasibility Study 20190503

Scope of Work

Modernization/additions to the existing 2081 seat (SRC) high school with 318,376 SF to create a 2600 student high school with 423,000 SF on the same site.

Project Details

  • Budget: $189,000,000 
  • Planning/Design Start: 2018 
  • Construction Start: TBD 
  • Phase & Percentage Complete: Planning; 95%
  • Current Status: Reviewing responses to the architectural/engineering Request for Proposal. Design of the school scheduled to commence Winter 2020.
  • Upcoming Activities: End-users, community members and the Project Planning Committee will be meeting with DCP team and Architect to develop the design for this high school.
  • Project Team:
    • Architect: TBD 
    • Contractor or Construction Manager: TBD 
  • PGCPS Contact: Joseph Wolf, Planner II
Project Documents

 

 


QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 1/27/2020 7:59:30 AM