Click here to view Suitland High School Groundbreaking Ceremony
School Information
- Principal: Ronald Hollis
- Address: 5200 Silver Hill Rd #2086,
District Heights, MD 20747
- Neighborhood: Suitland, Arnold Heights
- County Council District: District 7
(Rodney C. Streeter)
- State Legislative District: District 25
(Senator Melony G. Griffith, Delegates Darryl Barnes, Nick Charles, and Karen R. Toles)
- School Board Member: District 7 (Kenneth
Harris II)
Scope of Work
Full Replacement of
the existing 344,875 SF and 2,477 student Suitland High School Campus
consisting of Comprehensive High School (CHS), Center for Visual and Performing
(CVPA) Arts and Career Technical Education (CTE). The proposed design capacity
is 1,500 comprehensive and 500 CVPA students. The new facility will be one new
facility with the comprehensive and the CVPA school programs only. The CTE
programs will be relocated to Crossland High School for school year 2022 - 2023,
which will be designated as the new southern comprehensive CTE school for the
county.
Project Details
- Budget: $335,000,000.00 [BAS approved Not-To-Exceed (NTE)]
- Planning/Design Start: 2018
- Construction Start (multi-phased): Phase I - 2022; Phase II - 2024; Phase III - 2025
- Phase 1 Construction CHS (Projected: 5/2022-7/2024)
- Phase 2 Construction CVPA (Projected: 6/2024-12/2025)
- Phase 3 Construction Site (Projected: 6/2025-7/2026)
- Phase & Percentage Complete: Phase 1, 4% Complete
- Current Status: Submitted construction documents to Department of General Services for technical review/approval. Notice of Award and Notice to Proceed issued to construction manager. Awaiting balance of DPIE Permit approvals/releases to begin further Phase 1 Construction.
- Next Activities:
- Conduct Project Kick-Off Meeting (Completed: 2/23/2022)
- Issue GMP Pricing Set to CMAR (Completed: 3/4/2022)
- Vendor Outreach Event (Completed: 3/18/2022)
- Community Engagement Event (Completed: 4/5/2022)
- Student Engagement Event (Projected: 12/2022)
- Project Team: