International High School @ Langley Park
IHS SD 03-2019

 

Scope of Work

Construction of a new 58,000 sf, with a 400 SRC at International High School in Langley Park.

Project Details

  • Budget: $34,000,000 
  • Planning/Design Start: 2016 
  • Construction Start: February 2021
  • Phase & Percentage Complete: Design; 35%
  • Current Status: Design Development forwarded to MSDE for review and approval February 2021. The architect's construction document submission has been reviewed by internal design team and project manager.
  • Upcoming Activities: Department of Capital Programs is currently reviewing the drawings and providing comments back to the Architect for corrections. Construction Document phase completion anticipated Fall 2022.  
  • Project Team:
    • Architect: DLR Group
    • Contractor or Construction Manager: TBD 
  • PGCPS Contact: Hiwot Haileselassie, Project Manager II hiwot.haileselassie@pgcps.org

Project Documents


QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 7/15/2021 7:40:07 AM