Stephen Decatur Middle School SEI Renovation

 

Scope of Work

Special Education Inclusion Renovation: Renovate 11,240 net sq. ft. (17,000 GSF) in the southeast corner of the building for the CRI/Regional Program and an added space for the therapy pool to serve the regional students in the area.

Project Details

  • Budget: $10,501,000
  • Planning/Design Start: 2014 
  • Construction Start:  September 2020
  • Phase & Percentage Complete: Construction; 12%
  • Current Status: Permit for modulars is under review by third-party reviewer. Site work at auxiliary parking log ongoing. Swimming pool addition work activities in progress to include: installed plumbing groundwork, men's locker room, pouring of slab, and installation of electrical work for future construction phases. 
  • Upcoming Activities: Continue scheduled construction activities. 
  • Project Team:
  • PGCPS Contact: Henry Lewis, Project Manager II

QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 3/5/2021 8:50:55 AM