William S. Schmidt Outdoor Ed Center

WSC Cabins Front 05-2019(2)

Scope of Work

Modernization of and upgrades to the Center, to include construction of a second residential village, central dining hall, and environmental learning center as well as modernization of the Village I complex and modernization/adaptive reuse of the Orme Building.

Project Details

  • Budget: $32,000,000 
  • Planning/Design Start: 2016 
  • Construction Start: Spring 2021
  • Phase & Percentage Complete: Design; 75%
  • Current Status: Release solicitation documents to procure Construction Management services. 
  • Upcoming Actions: Continue project design and resolve permitting issues. Review construction management proposal responses and complete contract award. 
  • Project Team:
    • Architect: Quinn Evans
    • Contractor or Construction Manager: TBD 
  • PGCPS Contact: Joseph WolfPlanner II

Project Documents


QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 3/5/2021 9:17:30 AM