Andrew Jackson Academy HVAC Renovation

 

Scope of Work

Systemic Renovation: Replace 1971 HVAC equipment including one (1) chiller, 14 air handling units, heating and cooling piping, and the controls system, replace one (1) 1996 cooling tower, and replace two (2) 2000 steam boilers with hot water boilers.

Project Details

  • Budget: $17,641,000 
  • Planning/Design Start: 2016 
  • Construction Start:  September 2020
  • Phase & Percentage Complete: Construction; 90%
  • Current Status: In construction.
  • Upcoming Activities: HVAC Balancing and commissioning. 
  • Project Team:
  • PGCPS Contact: Henry Lewis, Project Manager II