Andrew Jackson Academy HVAC Renovation

 

Scope of Work

Systemic Renovation: Replace 1971 HVAC equipment including one (1) chiller, 14 air handling units, heating and cooling piping, and the controls system, replace one (1) 1996 cooling tower, and replace two (2) 2000 steam boilers with hot water boilers.

Project Details

  • Budget: $17,641,000 
  • Planning/Design Start: 2016 
  • Construction Start:  September 2020
  • Phase & Percentage Complete: Construction; 12%
  • Current Status: Working on piping at the hallways and boilers in the mechanical room. Structural supports for mechanical equipment at roof being installed. Temporary boiler installed but not connected. Phasing will be rearranged to allow for deletion of trailers.
  • Upcoming Activities: Cooling tower installation. Continue HVAC installation activities. 
  • Project Team:
  • PGCPS Contact: Henry Lewis, Project Manager II

QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 3/5/2021 10:22:00 AM