Stephen Decatur Middle School SEI Renovation
School Information
- Principal: Dr. Charity Magruder
- Address: 8200 Pinewood Drive, Clinton, MD
20735
- Neighborhood: Clinton
- County Council District: District 8 (Edward
Burroughs, III)
- State Legislative District: District 27 A
(Senator Michael Jackson, Delegate Elizabeth Proctor)
- School Board Member: District 9 (Sonya
Williams)
Scope of Work
Special Education Inclusion Renovation: Construction of a new
therapy pool addition, and renovation of the existing building in several
phases over approximately three years.
Project Details
- Budget: $15,105,800
- Planning/Design Start: 2014
- Construction Start: September 2020
- Phase & Percentage Complete: Construction; 75%
- Progress
to Date: Construction on the five classrooms called Phase 4 underway. Demolition completed. Underground plumbing, overhead electrical, CMU walls, and hollow metal frames under construction. Plumbing groundwork completed; MEP Rough-in’s completed; masonry walls at Science Classrooms completed. Scheduled to complete the last week of April.
- Current
Status: The completion date for the entire project is December 2022. Pool completion scheduled for July.
- Phase 1 Pool Addition: Plastering of the pool is the main construction activity remaining to be completed.
- Phase 4 :Classrooms completed.
- Phase 5: Kitchen completed and turned over to Food Services. New punchiest items.
- Phase 3 : Weight room completed. Restrooms completed.
- Phase 5: Entrance is complete except for exterior lighting and security.
- Phase 5a: demolition started.
- Phase 6: demolition started.
- Upcoming Activities:
- Pool Addition - Completion of overhead work,
ceiling close-in, and over all completion of pool.
- Phase 4 - Casework installation; painting,
ceiling grid, fixtures, diffusers to follow grid.
- Project Team:
- PGCPS Contact: Henry Lewis, Project Manager II henry2.lewis@pgcps.org