Stephen Decatur Middle School SEI Renovation

 

Scope of Work

Special Education Inclusion Renovation: Renovate 11,240 net sq. ft. (17,000 GSF) in the southeast corner of the building for the CRI/Regional Program and an added space for the therapy pool to serve the regional students in the area.

Project Details

  • Budget: $10,501,000
  • Planning/Design Start: 2014 
  • Construction Start:  September 2020
  • Phase & Percentage Complete: Construction; 60%
  • Current Status: Phase 1 - General construction of the addition continues: steel frame, CMU walls, roof, pool equipment, painting , ductwork, plumbing and casework completed. Phase 3 - Weight rooms and restrooms are near completion. Phase 4 - Renovation of five classrooms: demolition completed, construction underway. Phases 5- Kitchen completed and turned over to Food Services, entrance is complete with exception of exterior lighting thresholds and security. 
  • Upcoming Activities: Phase 1 - Continuation of addition construction, installation of pool deck. Phase 4 - Continue general construction. 
  • Project Team:
  • PGCPS Contact: Henry Lewis, Project Manager II henry2.lewis@pgcps.org

QUICK LINKS

 

 

DCP Logo

Louis Wilson Sr. Facilities Administration Building
13300 Old Marlboro Pike, Room 14
Upper Marlboro, Maryland 20772
T 301-952-6548 F 301-952-6526
E capital.programs@pgcps.org

 

Last modified: 1/13/2022 11:12:16 AM